SolarIndustry.ro / Case Study / Investment & Project Finance

Romanian utility-scale solar: bankability is shifting from capex efficiency to delivery and revenue quality.

Romania's solar market is not becoming unbankable; it is becoming more selective. The evidence now requires investors and lenders to distinguish a low-cost PV plant from a financeable power asset. Grid deliverability, project-weighted capture price, route-to-market structure, balancing allocation, counterparty quality and storage optionality increasingly determine debt capacity and equity resilience. A higher-capex project with firmer grid rights and better-shaped contracted cash flow can therefore be economically superior to a cheaper project exposed to an uncertain connection and an undifferentiated merchant-price assumption.

01 / Executive position

The asset class remains financeable. The generic underwriting approach does not.

Romanian PV has moved into a phase where revenue timing and deliverability deserve at least as much diligence as irradiation, EPC cost and nominal connection capacity.

Investment position: selectively bankable. Debt should be sized against stressed, project-weighted cash flow rather than an annual baseload price assumption. BESS should be valued as a site-specific option, not an automatic cure for merchant or grid risk.
Reported direct source observation Derived transparent calculation Judgement analyst conclusion Unknown requires project diligence
Judgement / revenue

Merchant exposure is no longer one variable.

Base-price level, solar shape, nodal or contractual basis, negative-price exposure, forecast error, imbalance settlement, curtailment treatment and route-to-market fees should be modelled separately. Compressing them into one “merchant discount” obscures where cash flow actually fails.

Reported + derived / grid

The connection queue is large; the advanced subset is much smaller.

ANRE reported 113,652 MW of maximum approved export power across 1,672 projects with valid ATRs at 1 July 2026. Only 11,153 MW sat at the combined connection-contract, construction-authorisation and establishment-authorisation stage: 9.8% of the ATR MW denominator. That ratio measures administrative progression, not probability of commissioning. [S02]

Reported / regulation

Development optionality now consumes more financial capacity.

ANRE's May 2026 reforms increased the financial guarantee associated with ATR issuance for relevant projects above 1 MW from 5% to 20% of the connection tariff excluding VAT, introduced an establishment-authorisation guarantee of €30/kW and specified a €20,000/MW capacity-allocation-auction guarantee for 2026. [S03]

Judgement / storage

Storage is valuable where it changes a specific exposure.

Romania already reported 924.43 MW / 1,762.50 MWh of storage by 1 July 2026. That increases the strategic relevance of BESS, but it also means a merchant-storage case must anticipate more competing flexibility. Avoided curtailment, capture uplift and ancillary-market revenue should each be evidenced independently. [S01]

02 / Current investment baseline

The market is scaling faster than a single “installed solar” number can describe.

The finance question is not whether Romania has room for more PV. It is which projects can convert a growing market into deliverable, contractable and financeable MWh.

Reported / 1 Jul 20263.84 GW

Gross photovoltaic capacity in Transelectrica's national generation-park breakdown; 3.737 GW net. This population is presented separately from prosumers. [S01]

Reported / 1 Jun 20263.897 GW

Installed prosumer power reported separately by Transelectrica. It should not be mechanically added to the generation-park PV figure without reconciling source definitions. [S01]

Reported / 1 Jul 2026924 MW

Installed storage power, paired with 1,762.50 MWh reported energy capacity. The implied fleet E/P ratio is approximately 1.91 hours; this is descriptive, not a recommended BESS duration. [S01]

Reported / 1 Jul 2026113.7 GW

Maximum approved export power represented by renewable projects with valid ATRs. It is a connection-process stock, not an executable construction pipeline. [S02]

The first underwriting error is mixing stocks.

The generation fleet, prosumer population, ATR queue, construction-authorised pipeline and advanced authorised pipeline answer different questions. A lender evaluating a 150 MW project needs to know what capacity can compete for the same grid corridor and market hours, but it should not treat every ATR MW as a future commissioned MW. Likewise, distributed prosumer capacity can affect residual daytime demand without being interchangeable with transmission-connected utility assets.

That distinction matters because solar's economic externality is increasingly temporal. Transelectrica explicitly linked the growing share of solar and wind production in H1 2026 with a greater share of short-term-market intervals exhibiting very low and even negative prices. [S01] The relevant risk is therefore not simply “more solar capacity”; it is correlated generation entering overlapping intervals faster than demand, interconnection, flexibility and storage can absorb it.

Investment implication. Future PV should be screened simultaneously against three competitive queues: the connection queue, the same-hour generation queue and the contracting/financing queue. A project can rank well on land and capex while losing on one of the other three.
03 / Market-shape evidence

The daytime price problem is visible before a project-specific capture model is built.

SolarIndustry's retained OPCOM evidence gives a screening signal. It must not be confused with a solar capture price because the 08:00–17:00 proxy is unweighted by actual project generation.

OPCOM PZU / 20 Jul–17 Aug 2026 / Romania / RON per MWhReported observations + SolarIndustry derived screen
Mean daily PZU base715.20RON/MWh · simple mean across 29 delivery days
Mean solar-window proxy371.47RON/MWh · unweighted 08:00–17:00 proxy
Proxy gap vs base48.1%Derived from means · not a capture-factor estimate
Negative PT15 evidence3 / 29delivery days; 51 negative 15-minute intervals in total
Solar-window pricing remained structurally below the daily base across the observation window Hover or focus
Romania PZU daily base price and unweighted solar-window price proxy, 20 July to 17 August 2026 The light line is the daily PZU base price. The yellow line is an unweighted 08:00 to 17:00 price proxy and is not a solar generation-weighted capture price. 1,000 750 500 250 0 -100 20 Jul 3 Aug 17 Aug
Source: SolarIndustry.ro retained OPCOM PZU delivery-day evidence. The yellow series is the platform's unweighted 08:00–17:00 solar-window proxy. It is a market-shape screen and not a project solar capture-price calculation. [S04]

What this evidence establishes—and what it does not.

Observed: daytime PZU prices can diverge materially from the all-day base price, and negative 15-minute intervals occurred during the selected 29-day period. Transelectrica separately reports that a greater solar and wind share has coincided with more very-low and negative short-term price intervals. [S01]

Derived: the simple average of the 29 daily solar-window proxies was approximately 48.1% below the corresponding simple average of daily PZU base prices. This is useful for screening the direction and potential magnitude of shape pressure.

Not established: a Romanian utility-scale PV plant would have captured 48.1% less than baseload. A real capture price depends on the project's quarter-hourly generation profile, outages, clipping, curtailment, settlement route, PPA mechanics, imbalance, basis and actual delivered MWh.

Underwriting rule. A baseload price forecast should never be inserted directly into a PV revenue model. The project needs a generation-weighted settlement model at the same temporal granularity as the commercial exposure.
04 / Capture-price architecture

Bankability begins with the correct denominator and the correct clock.

The investor needs to know what each generated MWh is worth when it arrives, not what an average MWh was worth during the year.

Separate market capture from net realised revenue.

Market capture price = Σ (project generationt × spot pricet) ÷ Σ project generationt
Capture factor = project market capture price ÷ chosen reference market price
Net realised revenue = merchant settlement + contractual settlements + qualifying flexibility revenue − imbalance charges − route-to-market fees − incremental operating costs

These equations should not be collapsed into one haircut. The capture factor addresses timing. It does not automatically include balancing, PPA basis, route-to-market cost, curtailment or BESS dispatch. A project-finance model that applies a generic capture discount to an already solar-shaped forecast can also double-count the same risk.

The minimum investment-grade capture study.

  • Quarter-hourly or finer generation profile. Use an independent energy-yield study and reconcile DC/AC ratio, clipping, degradation, availability and seasonal distribution.
  • Market-price chronology. Historic and forecast prices need consistent settlement intervals, timezone treatment and daylight-saving handling.
  • Forward cannibalisation mechanism. The forecast should explicitly respond to new PV, load growth, thermal retirements, hydro conditions, interconnection and flexibility rather than extrapolating one historic capture factor.
  • Contract mapping. Identify which MWh settle against spot, CfD reference price, PPA fixed price, floor, collar or other formula.
  • Physical-to-commercial reconciliation. Gross generation, auxiliary consumption, transformer losses, metered export, curtailed MWh and nominated volume should reconcile through one audit trail.
  • Downside correlation. Low prices, high solar output, curtailment and battery charging opportunities are not independent shocks. Stress cases should preserve plausible relationships.
Investment-grade rejection test. If a sponsor model cannot show how one quarter-hour of irradiance becomes one quarter-hour of metered energy, contractual settlement and CFADS, the revenue case is not sufficiently transparent for non-recourse debt.
05 / Merchant revenue risk stack

“Merchant risk” should be disaggregated before anyone prices it.

Each layer has a different hedge, different diligence owner and different failure mode.

Risk layerWhat can moveEvidence requiredPrimary mitigantBankability consequence
Base-price levelLong-run wholesale price curveIndependent market study, forward-market evidence, scenario assumptionsCfD, fixed-price PPA, floor, conservative debt caseControls the merchant tail's absolute revenue level
Solar shape / captureProject price relative to baseloadGeneration-weighted interval modelShaped offtake, storage, diversified generation profileCan impair revenue even if annual baseload forecast is unchanged
BasisDifference between project settlement and hedge/reference pointContract and market settlement mappingMatched settlement point/referenceCan leave an apparently “fixed” hedge economically open
Volume / profileGeneration differs from contracted shapeP50/P90 profile, PPA volume clausesPay-as-produced structure, tolerance bands, portfolio managementBaseload PPAs may create buy-back exposure
ImbalanceActual export differs from nominationForecast accuracy, BRP terms, historic imbalance costCompetent BRP, intraday optimisation, BESS where provenCash-flow volatility can increase despite a headline fixed price
Negative-price provisionsContract payment may change or cease in specified intervalsExact CfD/PPA drafting and settlement rulesDispatch, storage, contractual protectionsRequires contract-specific modelling; cannot be inferred from “fixed price” label
Curtailment / redispatchMetered export may be below available generationConnection terms, historical site/node evidence, compensation regimeGrid rights, compensation, BESS only where charging path is availableUnproven curtailment value should not support base-case debt
CounterpartyOfftaker fails, terminates or weakensCredit analysis, collateral, parent support, termination economicsInvestment-grade counterparty, LC/guarantee, replacement rightsA strong fixed price from a weak obligor can remain weak collateral

The balance between contracted and merchant cash flow is a debt-sizing choice.

A partially hedged project is not intrinsically weaker than a fully contracted one if the residual merchant tail is conservatively valued and debt amortisation is aligned with robust cash flow. Conversely, a long-tenor PPA does not eliminate risk if the volume obligation creates large profile settlements or the counterparty can terminate on weak security.

The correct investment question is therefore not “merchant or contracted?” It is: which exposures remain open after the contract, who carries them, and can debt service survive when those exposures move together?

06 / Offtake architecture

Revenue certainty is contractual engineering, not a label.

Romania now provides real precedents across CfD-backed, PPA-backed and wholesale-exposed solar. The public disclosures prove financing pathways exist; they do not establish universal leverage for every merchant project.

StructurePrimary benefitResidual exposureCritical lender diligence
Two-way CfDLong-tenor revenue stabilisation under the schemeContract-specific reference price, availability, settlement, compliance, excluded or merchant volumeEligibility, commissioning deadlines, settlement mechanics, security and termination
Pay-as-produced corporate PPACan fix or formula-price delivered renewable outputCounterparty credit, basis, imbalance, contract exclusions, merchant tailCredit support, tenor, change in law, curtailment, negative-price and termination clauses
Baseload / profiled PPACan produce predictable contracted volumeShape mismatch and buy-back risk when output differsHourly/quarter-hourly volume obligation and replacement-power economics
Floor / collarProtects a portion of downside while preserving defined upsideCounterparty, basis, settlement and residual tailWhether lenders recognise the floor as durable CFADS support
Partial hedge + merchant tailBalances contracted debt support and equity upsideUnhedged volume and post-hedge tenorDebt sizing to the contracted period and stressed merchant tail
Pure merchantFull market upside and contracting flexibilityAll price, shape and route-to-market riskIndependent market case, leverage tolerance, liquidity and refinancing assumptions
Observed financing spectrum. In November 2025 EBRD announced a €192 million financing package for three Romanian solar plants totalling 531 MW. Slobozia held a 15-year CfD; Corbii Mari and Iepuresti II were expected to sell power on the Romanian Day-Ahead Market. EBRD provided €64 million and mobilised €128 million from commercial lenders. [S07]

Interpretation: this transaction shows that institutional financing can accommodate different revenue profiles inside a Romanian solar financing package. Public disclosure does not provide enough detail on per-project ring-fencing, leverage, covenants, cross-support or downside assumptions to conclude that a standalone 100% merchant PV project would receive equivalent non-recourse terms.

07 / Contracted-revenue precedents

The financing market already distinguishes revenue structures.

Two public cases are more useful as evidence of lender behaviour than generic claims that “PPAs are bankable” or “merchant projects can finance.”

EBRD / Nov 2025 / financing package 531 MW

Three solar assets with €192 million financing announced. One plant benefited from a 15-year CfD while two were expected to sell on the Day-Ahead Market. The public source demonstrates mixed revenue architecture inside institutional financing, not a generic leverage benchmark. [S07]

EIB / approved Jun 2025 710 MWp

The Theia Solar Green Loan project covers three PV plants in Teleorman. EIB states that revenues will rely on commercial PPA(s) and wholesale-market sales. It also identifies environmental, cumulative-impact and promoter-capability appraisal. [S08]

CfD competition adds a separate benchmark—but not a merchant forecast.

Romania's second CfD auction, completed in August 2025 with EBRD support, awarded 2,751 MW. Combined first- and second-auction awards reached 4.2 GW. The second auction attracted more than 5.5 GW of solar and wind bids, with solar bids reported as low as €35/MWh. [S06]

The €35/MWh observation is a competitive bid result under a specific support structure. It should not be substituted for a wholesale-price forecast, universal PV LCOE or minimum price required by every project. What it does show is that contracted projects can compete aggressively for long-duration revenue stabilisation and that investors evaluating merchant projects should compare their risk-adjusted return against a growing body of state-supported contracted capacity.

08 / Grid queue

113.7 GW of valid ATR capacity is a headline. 11.2 GW at the deepest reported stage is the underwriting signal.

Administrative progression is not a commissioning probability, but it is a far better indicator of project maturity than the ATR headline alone.

Renewable projects ≥1 MW approved export power / 1 Jul 2026ANRE reported + SolarIndustry derived ratios
The queue narrows materially as projects move into binding delivery stagesMW / Romania
Romanian renewable grid-connection project capacity by administrative stage at 1 July 2026 Valid ATR capacity is 113,652 MW. Connection contracts represent 55,399 MW. Connection contracts plus construction authorisations represent 33,846 MW. The stage also holding ANRE establishment authorisations represents 11,153 MW. Valid ATR Connection contract + construction authorisation + establishment authorisation 113.7 GW 55.4 GW 33.8 GW 11.2 GW 0 50 GW 113.7 GW
Source: ANRE, status of renewable-generation projects with approved export power ≥1 MW, 1 Jul 2026. Ratios use 113,652 MW of valid-ATR approved export power as denominator. They are administrative-stage ratios, not estimated completion probabilities. [S02]
Reported55.4 GW

Maximum approved export power with connection contracts.

Reported33.8 GW

Connection contracts plus construction authorisations.

Reported11.2 GW

Connection contracts, construction authorisations and ANRE establishment authorisations.

09 / Grid deliverability

An ATR is evidence of a connection process. It is not a substitute for a deliverability model.

Investment-grade diligence has to identify what physically stands between the project and unrestricted, timely export.

The relevant asset is not merely “150 MW with an ATR.” It is a defined export entitlement attached to a defined substation, network topology, reinforcement programme, construction sequence, technical-compliance package and commissioning path.

Connection right

Verify: ATR validity, approved export/import power, point of connection, connection agreement, security package, milestones, change-control rights.

Failure mode: the project owns land and permits but cannot preserve or exercise the connection on the intended schedule.

Reinforcement dependency

Verify: exact network works, responsible party, procurement status, permitting, cost allocation, dependencies on third-party projects and long-stop date.

Failure mode: PV construction finishes before the grid work required for export.

Physical export

Verify: transformer rating, line capacity, substation configuration, N-1 implications, reactive-power requirements, protection and SCADA.

Failure mode: nominal approved MW cannot translate into expected operating profile under actual network conditions.

Operational restrictions

Verify: dispatch instructions, redispatch/curtailment provisions, compensation, outage coordination, metering and telemetry.

Failure mode: the model assumes all technically available generation is economically deliverable.

COD interface

Verify: energisation, testing, compliance certification, grid-code studies, punch-list and final acceptance.

Failure mode: EPC completion is mistaken for revenue commencement.

Base-case governance. This research did not identify a current public national dataset providing site- or node-specific Romanian solar-curtailment MWh at a resolution suitable for individual project underwriting. Until project/operator evidence establishes otherwise, avoided curtailment should not be a required base-case value source for a BESS investment.
10 / Connection reform

Speculative grid optionality now has a more visible liquidity cost.

ANRE's 2026 reform makes development-stage financial capacity part of the project-selection test.

ATR guarantee / reported20%

Financial guarantee for relevant production / consumption-and-production projects with approved export power above 1 MW increased from 5% to 20% of the connection tariff excluding VAT. [S03]

2026 capacity auction / reported€20k/MW

Guarantee specified for requested capacity in the 2026 allocation process. Application and transition details require project-specific legal confirmation. [S03]

Establishment authorisation / reported€30/kW

Financial guarantee based on installed power, valid until works reception and subject to the conditions set out in the reform. [S03]

Illustrative liquidity exposure for a 100 MW project.

At the stated 2026 capacity-allocation level, 100 MW corresponds to a €2.0 million auction guarantee. At €30/kW, a 100 MW establishment-authorisation guarantee corresponds to €3.0 million. The ATR-related amount cannot be calculated without the project's connection tariff.

These amounts should not automatically be added together: applicability, sequence, release and overlap depend on the project pathway and implementing rules. They are also not equivalent to permanently spent capex. They are nevertheless relevant to sponsor liquidity, guarantee-line availability, acquisition pricing and the cost of warehousing a development portfolio.

Milestone asymmetry remains important.

ANRE's reform also set deadlines for obtaining establishment authorisations and provided for extensions in justified cases. Separately, the framework allows the network operator to seek successive 12-month extensions where connection or reinforcement works for which it is responsible require more time. [S03]

Financing implication. A sponsor can face harder milestone and collateral discipline while still carrying schedule exposure to network-operator works. Acquisition documents, EPC notice to proceed, PPA start dates and financing long-stop dates should therefore be conditioned on grid milestones that the project can actually evidence.
11 / Grid geography

Connection quality is locational, not national.

A Romania-wide grid narrative is inadequate for underwriting a project tied to one substation and one reinforcement sequence.

Transelectrica's H1 2026 report explicitly identifies Dobrogea in the south-east and Banat in the south-west as regions with strong wind and solar potential that are already congested and, under existing conditions, do not allow integration of additional capacities. The company states that investments under way and planned for those regions are expected to provide approximately 5,000 MW of additional integration capacity by 2027. [S01]

The 5,000 MW figure is planned additional integration capacity, not commissioned renewable generation, not an allocation to any named developer and not a guarantee that each current ATR will become deliverable. The schedule, technical scope and dependency of the exact project on those reinforcements remain diligence items.

What a locational grid memorandum should contain.

  • single-line diagram from project transformer to the relevant upstream network;
  • existing and planned generation connected to the same electrical area;
  • all network upgrades embedded in the project's ATR and connection agreement;
  • network-owner responsibility and evidence of procurement or construction status;
  • planned outage and energisation sequence;
  • import capability if BESS is contemplated;
  • export cap treatment when PV and BESS share the connection;
  • reactive power, fault ride-through, protection, SCADA and telemetry requirements;
  • operational restriction, redispatch and curtailment language;
  • contractual remedies if grid completion misses the project long-stop date.
Acquisition principle. A mature connection position can justify a higher development premium only when its legal durability and physical deliverability are demonstrated. Paying for “scarce grid” without reconstructing the network dependency simply capitalises an unverified assumption.
12 / BESS market context

Storage optionality is becoming part of the asset design. Merchant storage scarcity should not be assumed to persist.

The current fleet and policy pipeline support a stronger flexibility market. They also create a competitive response that storage investors must model.

Storage power / 1 Jul 2026924.43 MWTranselectrica reported
Storage energy / 1 Jul 20261,762.50 MWhTranselectrica reported
Fleet E/P / derived1.91 hdescriptive ratio only
Projects with storage / ANRE subset15511,268.7 MW approved export power across plants with storage and standalone storage; not BESS MW

ANRE reported that, among the 673 projects with connection contracts and construction authorisations in its 1 July 2026 dataset, 155 projects representing 11,268.7 MW of maximum approved export power had been reported by network operators as plants with storage installations or standalone storage. Forty of those projects, representing 3,143.2 MW of approved export power, were reported as expected to commission in 2026. [S02]

Those MW figures describe project approved export power, not the energy capacity or discharge power of the batteries themselves. Treating 11.27 GW as a BESS-capacity pipeline would be a denominator error.

Policy is also supportive. The European Commission's published state-aid record for SA.121308 describes a Romanian Modernisation Fund scheme for standalone battery-storage investment, with an overall budget of RON 764.295 million and duration through 31 December 2030. [S09] ANRE had already removed specified double network charging for electricity stored and subsequently reinjected, while retaining network tariffs for the storage facility's own consumption including technological losses. [S10]

Second-order effect. More storage can improve solar integration and create project-level optionality. The same deployment can eventually compress some arbitrage spreads and scarcity rents that early storage models rely upon. That competitive compression is a forward hypothesis—not an observed certainty—and should be included as a downside scenario rather than presented as a deterministic outcome.
13 / What BESS can actually hedge

Storage creates value only when the project can name the exposure it changes.

A BESS business case should be decomposed into independently testable value pools.

Value poolEconomic mechanismEvidence needed before base-case inclusionKey failure mode
Capture-price upliftMove energy from low-value PV intervals into higher-value intervalsInterval PV profile, price forecast, charging constraints, efficiency, degradation, cycling policySpread compression or insufficient discharge headroom
Clipping recoveryCapture DC generation that would otherwise be clippedDC/AC design, clipping study, battery topology and charging limitsClipping volume too small to justify battery cost
Curtailment recoveryCharge energy that would otherwise be curtailed and discharge laterVerified site/node curtailment pattern and technical ability to charge during restrictionCurtailment is assumed rather than observed, or restriction also prevents charging/export
Imbalance reductionUse battery flexibility to reduce deviation between nomination and deliveryBRP settlement data, forecast error distribution, dispatch rightsBattery is committed to other services when imbalance occurs
Ancillary / balancing servicesProvide reserve or balancing productsQualification, market rules, price history, availability requirement, optimizer capabilityMarket depth and prices decline as flexible capacity enters
Connection utilisationShare an export cap between PV and battery across timeConnection agreement, metering, import/export rights and dispatch studyContractual or technical restrictions prevent expected stacking
Contract shapingUse storage to better match a PPA or other delivery profileContract nomination, tolerance and settlement termsBattery degradation cost exceeds avoided shape penalty
Base-case standard. A value pool enters the debt case only after the project can demonstrate the right, the physical capability, the market access and a conservative revenue assumption. “BESS adds flexibility” is a strategic statement, not a bankable revenue line.
14 / Build now or preserve the option?

Storage-ready can be the rational answer when BESS is not yet finance-positive.

The decision should separate irreversible construction from reversible design optionality.

ConfigurationBest fitAdvantagesPrimary diligence concern
PV onlyStrong capture economics, contracted revenue or weak BESS value caseLower capex and operational complexityLeaves future timing risk unhedged
PV storage-readyStorage value plausible but timing/economics uncertainPreserves future option through land, electrical design, control architecture and permitting strategyOption must be real: reserved space without grid/import rights may have little value
AC-coupled BESSIndependent dispatch and retrofit flexibility matterOperational separation from PV conversion systemAdditional conversion losses, connection/import-export treatment and metering
DC-coupled BESSClipping recovery and integrated PV charging are importantPotentially efficient use of shared equipment and clipped energyDesign complexity, availability interaction and support-scheme/PPA metering
Standalone BESSStorage economics do not depend on a PV assetIndependent siting and market optimisationSeparate grid access and stronger dependence on standalone merchant value pools

The investment committee should demand the counterfactual.

A co-located battery should be compared with PV-only and PV-storage-ready alternatives using the same market path. If BESS generates its return primarily by assuming historically exceptional price spreads, unverified curtailment or persistent ancillary scarcity, the value case is fragile. If the battery materially improves a contracted delivery obligation, preserves generation otherwise demonstrably lost, or creates a durable revenue floor, the case is stronger.

Storage also introduces new liabilities: degradation, augmentation, warranty throughput limits, availability guarantees, fire-safety requirements, EMS/optimizer dependence, auxiliary consumption, replacement capex and residual-value uncertainty. The project should not treat battery capex as the only incremental cost.

15 / PPA, CfD and BESS interaction

A battery cannot be assumed to “shift contracted solar” until the contract says it can.

Commercial eligibility, metering and dispatch rights have to be mapped before storage optimisation is valued.

Questions that must be answered contract by contract.

  • Which meter determines qualifying generation and contractual settlement?
  • Can the BESS charge from the grid, PV only, or both?
  • If grid-charged energy is later exported, how is it distinguished from renewable generation?
  • Who controls BESS dispatch: project company, offtaker, BRP or optimizer?
  • Can battery dispatch cause the project to miss PPA delivery obligations?
  • How are negative-price intervals treated by the offtake contract or support arrangement?
  • Does BESS cycling change the contractual availability calculation?
  • Does charging during a grid restriction remain physically and contractually possible?
  • How are storage losses, auxiliary consumption and metered imports allocated?
  • Who receives ancillary-service revenue and who carries associated imbalance?

The answers determine whether storage is a hedge, a separate merchant business or both. They also determine whether the battery improves debt service or merely moves value between equity revenue streams.

Legal diligence point. Do not infer CfD or PPA treatment for stored electricity from the existence of a PV contract. Eligibility, settlement and metering must be confirmed against the executed agreement and applicable rules. Romania's CfD scheme itself has been implemented through specific state-aid and tender documentation. [S11]
16 / Investment-grade model architecture

The model should be auditable from irradiance to debt service.

A finance model that starts with annual MWh and annual price has already aggregated away several of the risks that now matter most.

LayerCore inputsRequired outputControl test
1. ResourceIrradiance, temperature, interannual variabilityInterval resource seriesIndependent source and long-term correction
2. Energy yieldModule/inverter model, losses, degradation, availabilityP50/P90 generation profileIndependent engineer reconciliation
3. Grid exportExport cap, outages, auxiliary load, verified curtailment assumptionsMetered export MWhConnection agreement and single-line consistency
4. MarketQuarter-hourly prices, capture model, basisMarket value of each intervalNo direct use of annual baseload for PV output
5. ContractPPA/CfD formula, volume, tenor, floors/collarsContract settlementFinancial model matches executed legal drafting
6. BalancingForecast error, BRP terms, intraday correctionImbalance and route-to-market costEvidence from BRP offer or operating history
7. BESSPower, energy, efficiency, degradation, augmentation, dispatchIncremental cash flow by value poolNo double counting of PV revenue or avoided curtailment
8. Opex / taxO&M, land, insurance, network charges, tax, inflationEBITDA and CFADSContracts and advisor tax model
9. FinancingDrawdown, fees, interest, reserve accounts, amortisationDSCR, LLCR, debt balanceTerm-sheet mechanics reproduced exactly
10. EquityAcquisition price, development spend, distributions, exit assumptionsEquity cash flow and return metricsNo refinancing or terminal-value assumption hidden in base case
Model governance. Keep reported data, independent forecasts, sponsor assumptions and analyst overrides in distinct input classes. Every material derived metric should be reproducible. A debt case should never be constructed by manually reducing the final EBITDA line because the underlying risk cannot be traced.
17 / Debt sizing

Debt capacity should emerge from cash-flow resilience, not from a target leverage ratio.

There is no defensible universal Romanian solar DSCR threshold that can be imposed across lenders, revenue structures and project stages.

DSCR = Cash Flow Available for Debt Service ÷ Scheduled Debt Service
LLCR = NPV of CFADS over the loan life ÷ Debt outstanding at the measurement date

Those formulas are standard; the thresholds are deal-specific. A lender may distinguish contracted and merchant periods, P50 and downside generation, different price forecasts, reserve requirements and amortisation profiles. The report therefore does not manufacture a “market standard” minimum ratio unsupported by a current term-sheet dataset.

A stronger debt-sizing sequence.

  1. Build a sponsor base case from fully reconciled physical and commercial assumptions.
  2. Create a lender energy case using the independent yield methodology required by the financing process.
  3. Replace sponsor merchant assumptions with the lender-approved market case or agreed haircut methodology.
  4. Apply the executed offtake terms, including termination, negative-price and volume mechanics.
  5. Apply project-specific grid availability and curtailment treatment rather than a generic national assumption.
  6. Model imbalance and route-to-market costs explicitly.
  7. Include BESS revenue only to the extent accepted by the lender and supported by contracts or conservative evidence.
  8. Size and sculpt debt to the required coverage profile.
  9. Run combined downside cases before determining distributable equity.
Key distinction. A project can be economically attractive and still have limited non-recourse debt capacity. Equity bankability and debt bankability are related but not identical decisions.
18 / Stress-testing framework

Single-variable sensitivities are useful diagnostics. They are not a downside case.

The major Romanian solar risks can reinforce one another. The model should show the combined cash-flow effect.

StressPrimary variableCorrelated variables to considerEarly-warning evidence
Solar cannibalisationCapture factor weakensMore negative intervals, charging competition, PPA repricingProject-weighted capture trend vs baseload
Low wholesale caseMerchant price curve declinesLower BESS arbitrage revenueForward curve and independent forecast revisions
Grid delayCOD moves laterIDC, EPC claims, PPA start mismatch, guarantee extensionNetwork works critical-path slippage
Export restrictionDelivered MWh fallsCapture mix, PPA volume, BESS charging opportunityOperator notices and actual node restrictions
Balancing shockImbalance cost risesForecast error and intraday liquidityBRP settlement history
PPA counterparty eventContract cash flow lost or delayedReplacement price, collateral draw and merchant exposureCredit rating, financial statements, collateral status
EPC / capex overrunConstruction cost increasesContingency, sponsor equity, delayProcurement packages and schedule contingency
BESS revenue compressionArbitrage/ancillary value declinesCycle count, degradation and optimizer economicsSpread distribution and qualified flexible capacity
BESS degradationUsable MWh declines fasterAugmentation capex and warranty claimsSOH and throughput versus warranty curve
Interest / refinancingDebt cost or terminal refinancing worsensCoverage and equity distributionsHedge coverage and maturity profile
Red-team requirement. The investment case should identify the combination of events that causes the first covenant breach, the first equity distribution lock-up and the first permanent loss of capital. If management only knows the sensitivity that reduces IRR by one percentage point, the downside has not been analysed deeply enough.
19 / Contract risk allocation

Every model assumption needs a contract owner—or it remains equity risk.

Bankability improves when construction, operational and revenue risks are placed with parties capable of controlling them and backed by enforceable remedies.

ContractRisk to allocateBankability provisionsResidual diligence
EPCCost, schedule, performanceFixed-price scope where achievable, LDs, performance tests, security, interface matrixCap, exclusions, relief events, contractor credit
Module / inverter supplyEquipment performance and defectsBankable warranty, degradation/performance terms, assignabilityManufacturer credit and claims process
O&MAvailability and responseAvailability KPI, response times, spare-parts strategyExclusions and interface with OEM warranties
ConnectionGrid scope, timing and costDefined milestones, responsibilities, security and remediesOperator extension rights and reinforcement dependencies
PPA / CfDPrice, volume and counterpartyClear settlement, credit support, change-in-law and termination regimeResidual market/basis exposure
BRP / route-to-marketNomination and imbalanceTransparent fee, data access, settlement and terminationIncentive alignment and historic performance
BESS OEM / integratorAvailability, degradation, throughputCapacity/efficiency guarantees, augmentation and warranty regimeSOH definition, excluded operating modes, warranty security
OptimizerDispatch and market accessRights, revenue definition, benchmark, data ownership, terminationMerchant forecast risk remains with project unless guaranteed
20 / Technical due diligence

The independent engineer now needs to test commercial consequences, not only plant performance.

Technical diligence should explain how design decisions alter capture, export and contractual settlement.

Energy

Yield and profile

P50/P90, interannual variability, hourly/quarter-hourly generation, degradation, clipping, availability and loss stack.

Grid

Connection and dynamic compliance

Studies, protection, reactive power, fault ride-through, SCADA, metering, export/import limits and commissioning sequence.

Build

Constructability

Geotechnical, drainage, flood, access, civil scope, cable routes, substation delivery and critical-path procurement.

Equipment

Technology bankability

Track record, warranties, degradation, supply-chain quality, spares, service capability and replacement assumptions.

Storage

BESS duty-cycle validation

Power/energy sizing, SOH, round-trip efficiency, thermal management, augmentation, safety and warranty throughput.

Revenue interface

Meter-to-model reconciliation

Demonstrate how the technical export profile maps into the revenue model and contracted settlement.

21 / Legal, tax and E&S diligence

Investment-grade solar is a rights package, not merely an engineered plant.

Land, permits, grid rights, environmental obligations and revenue contracts have to survive financing and enforcement.

Legal diligence priorities.

  • land ownership or lease chain, cadastral status, access and easements;
  • urbanism, construction and establishment authorisations and their expiry/milestone conditions;
  • ATR and connection-contract transferability and change-of-control implications;
  • security package, lender step-in and direct agreements;
  • PPA/CfD assignability, termination payments and lender cure rights;
  • corporate approvals, shareholder funding commitments and guarantee availability;
  • BESS permitting, fire-safety, hazardous-material and emergency-response obligations where applicable.

Environmental and social diligence is finance diligence.

EIB's public Theia project summary states that its appraisal addresses the EIA screening process, potential cumulative impacts, impacts on nature-conservation sites and the promoter's capacity to implement the project. [S08] For lenders and institutional investors, environmental or biodiversity defects can become permitting delay, capex, operating restriction, litigation or reputational exposure. They therefore belong in the project model and conditions-precedent schedule rather than an annex completed after commercial underwriting.

Tax diligence should follow cash flow.

Model reviews should reconcile tax assumptions with SPV structure, financing, depreciation, VAT timing, land arrangements, revenue contracts, BESS charging and any applicable support scheme. This report does not prescribe project-specific Romanian tax treatment; current advice should be obtained for the actual ownership and financing structure.

22 / Bankability archetypes

The future Romanian PV market will bifurcate by evidence quality.

These classifications are strategic judgements, not lender ratings. They identify what would normally need to be true before a project can move toward investment-grade financing.

ArchetypeRevenueGridStorageFinancing view
A / Contracted + deliverableLong-tenor credible offtake with controlled residual exposuresMature rights, defined works and credible CODOnly if additiveStrongest project-finance candidate, subject to full diligence
B / Partially contracted + mature gridContract supports debt period; merchant tail conservatively modelledDeliverability substantially evidencedOptional or targetedFinanceable with disciplined debt sizing
C / Merchant + strong gridProject-weighted merchant case and liquidity supportMature and deliverablePotential hedgePossible for suitable capital; leverage likely more sensitive to market assumptions
D / Contracted + weak gridStrong headline offtakeMajor unresolved reinforcement or COD dependencyCannot automatically solveConditional; contract value may not be realisable on time
E / Merchant + speculative gridHigh open price/capture exposureImmature or uncertainOften presented as a remedyDevelopment optionality rather than finance-ready asset
Core conclusion. A project's bankability should increasingly be expressed as the quality of five rights: the right to build, the right to connect, the practical ability to deliver, the contractual right to monetise, and the financing right to survive downside. Storage can improve several of those economics, but it cannot repair a missing legal or physical right.
23 / Investment committee gates

Replace one blended project score with seven evidence gates.

A project should be able to fail one gate without a strong score elsewhere disguising the problem.

Gate 1 / Rights

Land, permits, establishment authorisation and corporate rights are valid, transferable where needed and aligned with financing.

Stop condition: critical rights expire before realistic construction or cannot be secured by lenders.

Gate 2 / Grid

Connection terms, reinforcement scope, schedule, export cap and operator dependencies are independently mapped.

Stop condition: COD depends on an unverified network assumption.

Gate 3 / Energy

Independent yield, degradation, availability and interval profile support the revenue case.

Stop condition: project economics require sponsor yield materially above independent evidence.

Gate 4 / Revenue

Capture, PPA/CfD, merchant tail, basis, imbalance and negative-price exposure are transparent.

Stop condition: baseload forecast is used as project realised price without an interval model.

Gate 5 / Buildability

EPC scope, capex, schedule, equipment and contractor credit are financeable.

Stop condition: residual interfaces exceed sponsor contingency or critical procurement is unsecured.

Gate 6 / Storage

Each BESS value pool is evidenced and contractually available; degradation and augmentation are funded.

Stop condition: equity case depends mainly on unverified curtailment or persistent extreme spreads.

Gate 7 / Finance

Debt case survives combined downside with adequate liquidity and covenant headroom.

Stop condition: required leverage exists only in sponsor base case.

24 / Acquisition diligence

Development-stage M&A should price evidence, not MW.

The connection queue makes apparent pipeline scale easy to acquire on paper. The value lies in de-risked progression.

Purchase-price allocation should distinguish four things.

Recoverable project spend. Land, studies, applications and engineering may have evidence value but do not automatically equal market value.

Scarce rights. A durable grid position, permits and land package can justify a development premium when independently verified.

Execution work completed. Advanced engineering, procurement and network works reduce remaining schedule risk only to the extent they are usable by the buyer.

Speculative option value. Pipeline projects dependent on future auctions, reinforcement or unresolved permits should be valued as options with explicit failure pathways rather than at a uniform €/MW benchmark.

Earn-outs can align value with evidence.

For immature projects, consideration can be linked to objective milestones: preservation of grid rights, construction authorisation, establishment authorisation, financing-ready offtake, notice to proceed, energisation or COD. The exact mechanism is transaction-specific, but the principle prevents the acquirer from paying full finance-ready value before the project has crossed finance-ready gates.

Due-diligence warning. ANRE's 113.7 GW valid-ATR stock versus 11.2 GW at the deepest reported stage is a market-level reminder that nominal pipeline MW and executable MW are not equivalent. [S02]
25 / Forward view / 2026–2030

The direction is investable. The dispersion between projects should widen.

These are scenario frameworks rather than probability-weighted forecasts. They identify what would change the bankability conclusion.

Base case

Conditions: Romanian PV and BESS deployment continues; grid reinforcements progress unevenly; capture pressure becomes a permanent underwriting variable; CfD/PPA financing coexists with merchant exposure.

Implication: contracted and grid-mature assets retain strong financing access, while merchant projects require lower leverage, stronger sponsor liquidity or differentiated capture/storage economics.

Upside

Conditions: transmission reinforcement, interconnection, demand growth and flexible load/storage absorb solar output faster than expected; corporate PPA depth expands; balancing/route-to-market capability improves.

Implication: capture erosion moderates and well-sited merchant projects regain debt capacity. Storage value shifts from scarcity trading toward contracted shaping and grid services.

Risk case

Conditions: PV additions outpace flexible demand and grid reinforcement; low/negative daytime intervals become more frequent; network works slip; storage merchant revenues compress as competition increases.

Implication: merchant PV valuations fall first at weak nodes. Debt migrates toward CfD/PPA-backed projects and acquisitions place larger discounts on immature connections.

Structural break

Conditions: material market-design, network-tariff, support-scheme, balancing or connection-allocation changes alter the economics faster than historical models can capture.

Implication: existing long-term assumptions require re-underwriting. Projects with flexible contractual structures, strong grid rights and low fixed leverage preserve more strategic options.

26 / Red-team pre-mortem

Assume the investment disappoints. What probably went wrong?

The most useful red team attacks the project's hidden dependencies rather than repeating generic risk factors.

FailureHow it becomes visibleWhy the original case missed itContingency
Capture deteriorates faster than forecastProject-weighted price falls relative to referenceModel relied on annual baseload or static capture factorRe-contract, optimise availability, add storage only if incremental case clears
Grid COD slipsReinforcement milestones repeatedly moveOperator work was treated as a date rather than a critical pathLong-stop protections, staged NTP, sponsor liquidity buffer
PPA hedge performs poorlyShape or imbalance settlements consume fixed-price benefitHeadline price was analysed without settlement mechanicsRenegotiate shape, improve forecasting/BRP, use BESS selectively
BESS merchant case compressesSpread and ancillary revenue fall as competing storage growsHistorical scarcity was extrapolatedPreserve multiple value pools, contracted optimisation, lower leverage
Guarantee / collateral burden growsDevelopment portfolio consumes bank linesGuarantees treated as immaterial because not capexStage portfolio, recycle weak projects, allocate liquidity by milestone quality
Debt case depends on refinancingCoverage is adequate only with optimistic terminal debtRefinancing was embedded as a certaintyAmortise to resilient cash flow and treat refinancing as upside
27 / Portfolio expansion

The portfolio should diversify electrical and contractual risk, not just geography.

Ten projects in different counties can still be one economic exposure if they generate into the same hours under the same market structure.

Portfolio construction should track five concentrations.

Node and network concentration. Projects should be mapped by electrical dependency and shared reinforcement, not only map coordinates.

COD concentration. A portfolio with the same delivery year can be exposed to the same equipment, financing, auction and connection bottlenecks.

Revenue concentration. Diversify CfD, corporate PPA and merchant exposure deliberately rather than inheriting a portfolio-wide merchant tail.

Counterparty concentration. Several PPAs with one buyer do not diversify credit risk.

Shape concentration. South-facing PV assets produce highly correlated hours. Tracking configuration, geographic weather diversity, storage and complementary generation can change the aggregate capture profile, but the effect should be modelled rather than presumed.

Preferred expansion sequence.

  1. Prioritise projects with durable connection rights and independently evidenced delivery schedules.
  2. Secure or design credible revenue protection before maximising leverage.
  3. Preserve storage-ready optionality at sites where flexibility may become valuable but BESS does not yet clear the investment hurdle.
  4. Acquire immature connection positions only at prices consistent with milestone failure risk.
  5. Measure portfolio capture and balancing exposure at interval level.
  6. Allocate guarantee-line capacity to projects with the highest probability-adjusted strategic value rather than largest headline MW.
28 / 90-day transaction workplan

Move from market thesis to bankable evidence in four workstreams.

The sequence is designed to kill weak assumptions before expensive financing work is committed.

Days 0–20

Grid and rights reconstruction. Build the connection critical path, permit matrix, land chain and guarantee schedule. Obtain underlying operator correspondence and technical studies.

Decision: confirm whether the project deserves further diligence.

Days 10–35

Interval revenue model. Rebuild yield and settlement at quarter-hourly level; calculate project capture, merchant tail, PPA/CfD settlement, imbalance and downside.

Decision: establish an investable revenue case independent of sponsor summary outputs.

Days 20–50

Technical and commercial diligence. Validate EPC, equipment, O&M, BRP, offtake and BESS design; reconcile model assumptions to contracts.

Decision: determine residual risks that remain with SPV equity.

Days 40–70

Financing market test. Issue lender information package based on a reconciled model, not sponsor headline returns. Obtain term-sheet feedback on merchant tail and storage revenue treatment.

Decision: establish actual debt capacity and lender conditions.

Days 60–90

Investment committee and documentation. Run combined downside, finalise conditions precedent, price residual risk and negotiate acquisition/EPC/PPA protections.

Decision: approve, reprice, defer or reject.

29 / Implications by audience

Bankability now changes what each capital provider should ask first.

The diligence order matters because each audience is exposed to a different failure point.

Infrastructure investors

Pay for delivery quality.

Value grid maturity, contract durability and project-weighted capture before optimising acquisition €/MW. Use milestone-linked consideration where execution evidence is incomplete.

Lenders

Underwrite residual exposures.

Ask what remains open after the PPA/CfD, size debt to stressed CFADS and require explicit treatment of capture, imbalance, grid delay and merchant tail.

Renewable energy funds

Portfolio-manage correlation.

Monitor node, capture, counterparty, COD and merchant concentrations. Project count and geographic spread alone can materially overstate diversification.

Project-finance teams

Reconcile every layer.

Make the model, technical report, connection documents and revenue contracts tell the same story at the same settlement granularity.

30 / Final investment position

The winning Romanian PV asset will not necessarily be the cheapest plant.

Its advantage will be the quality and durability of the cash-flow system around the plant.

Romanian utility-scale solar remains an investable asset class. The current evidence does not support a thesis that merchant exposure, grid congestion or storage competition make new PV structurally unfinanceable. It does support a more demanding conclusion: financeability is becoming increasingly project-specific.

The market now contains enough solar for same-hour price effects to matter, enough connection demand for grid progression to carry economic value, enough storage for flexibility to become both a hedge and a competitive market, and enough financing precedent to show that strong projects can still attract institutional capital under different revenue structures.

The resulting underwriting standard is clear. A future PV investment should not be approved because the sponsor can show an attractive annual yield, a valid ATR and a long-run average power price. It should be approved when the investment committee can trace the physical MWh through the grid, the settlement MWh through the revenue contract and the stressed cash flow through debt service.

Decision rule. Prefer the project with demonstrably deliverable MWh and resilient realised revenue over the project with the lowest headline capex. Preserve BESS optionality where it has plausible future value; build it when specific, evidence-backed value pools clear the return and financing hurdle.
31 / Method, limitations & evidence

What is known, what is derived and what still belongs in the data room.

The report prioritises current primary and institutional evidence. Public market data are used to frame underwriting questions, not to replace project-specific technical, legal or lender diligence.

Evidence confidence / high

Current reported market structure

Installed fleet, storage stock, grid-connection stages, current guarantee reform and cited public financing transactions are directly supported by primary or institutional sources.

Evidence confidence / medium

Structural interpretation

Capture-price pressure, storage competition and likely financing bifurcation are analytical conclusions supported by current observations but remain sensitive to future grid, demand, policy and market development.

Evidence confidence / project-specific

Bankability outcome

Node-level curtailment, exact reinforcement schedule, project capture factor, PPA settlement, lender leverage, DSCR thresholds and BESS revenue are unknown until the actual project and contracts are diligenced.

Method.

Primary-source evidence was prioritised from Transelectrica, ANRE, Romania's Ministry of Energy and EU institutional records. EBRD and EIB disclosures were used for financing precedents. SolarIndustry.ro's retained operational history was used as a traceable market-observation layer. The SolarIndustry hourly history averages all retained public Transelectrica readings recorded during each local Europe/Bucharest hour; missing hours are left absent rather than interpolated. PZU data are maintained separately because they are delivery-day market results. [S04]

Price-screen methodology.

The 20 July–17 August 2026 exhibit uses 29 OPCOM PZU delivery days retained by SolarIndustry. “Solar window” is the platform's unweighted 08:00–17:00 price proxy. The report calculates simple means across those daily observations and compares the resulting solar-window mean with the mean daily PZU base price. This does not weight prices by project output and must not be used as a project capture factor.

Grid-pipeline methodology.

ANRE's 1 July 2026 maximum approved export power is shown by administrative stage. Derived percentages divide the capacity at each stage by 113,652 MW of valid-ATR approved export power. The ratios describe stage progression only. They do not estimate a project's probability of construction or imply that capacity falling outside a later stage has been cancelled.

Material limitations.

No current public source identified in this research provides the site-specific quarter-hourly generation, curtailment, PPA settlement, BRP cost, nodal reinforcement schedule, debt terms or BESS operating data required to make an investment decision on a named project. The 29-day price screen is deliberately short relative to an asset life and is used only to demonstrate current market shape. Historic observations should not be extrapolated mechanically over a financing tenor.

Regulation can change. The May 2026 ANRE communication is used as evidence of the adopted connection/licensing reform, but a transaction should verify the final implementing order, effective dates, transitional treatment and applicability to the project with Romanian counsel.

Use limitation. This is independent market and decision research, not investment, legal, tax, accounting or technical advice. Project finance requires asset-specific lender, legal, tax, market and independent-engineer diligence.
32 / Source register

Auditable evidence ledger.

Research cut-off: 17 Aug 2026. Source dates and observation dates are kept distinct where material.

  1. S01
    Transelectrica — Half-yearly Report January–June 2026. Report dated 14 Aug 2026. Used for national generation-park capacity at 1 Jul 2026, storage capacity, prosumer stock, short-term low/negative-price commentary, balancing-price volatility context and grid-development/congestion statements. Primary public-system/operator evidence.
  2. S02
    ANRE — Status of renewable electricity-generation projects with approved export capacity ≥1 MW at 1 Jul 2026. Used for valid ATR count and MW, connection-contract stages, construction/establishment-authorisation stages, projects reported with storage and expected commissioning distribution. Primary regulator evidence.
  3. S03
    ANRE — Connection and licensing regulation reform communication, 21 May 2026. Used for 20% ATR-related financial guarantee, establishment-authorisation deadlines and €30/kW guarantee, 2026 allocation-auction guarantee and grid-operator extension provisions. Project applicability requires legal verification.
  4. S04
    SolarIndustry.ro — Romania operational electricity data history. Retrieved through research cut-off 17 Aug 2026. Used for retained OPCOM PZU daily evidence and methodology. Original operational source is Transelectrica; original PZU source is OPCOM. The displayed solar-window series is explicitly an unweighted screening proxy, not a solar capture-price calculation.
  5. S05
    OPCOM — Romanian electricity market operator. Original public market source for PZU delivery-day and PT15 evidence retained and analysed in the SolarIndustry data-history layer.
  6. S06
    EBRD — Romania's second renewable CfD auction, 21 Aug 2025. Used for 2,751 MW second-auction award, 4.2 GW combined first/second awards, >5.5 GW bids and reported solar bid prices as low as €35/MWh. Institutional secondary / transaction-framework evidence.
  7. S07
    EBRD — €192 million Romanian solar financing package, 27 Nov 2025. Used for the 531 MW Slobozia, Corbii Mari and Iepuresti II package, EBRD/commercial lender participation, Slobozia CfD and disclosed Day-Ahead-Market exposure for the other projects.
  8. S08
    European Investment Bank — Theia Solar Green Loan. Project summary released 6 Mar 2025; approved 19 Jun 2025. Used for 710 MWp Teleorman portfolio, commercial PPA(s) plus wholesale-market revenue architecture and EIB environmental/social appraisal topics. Public financing-project evidence; financing amount not disclosed.
  9. S09
    Official Journal of the European Union — State aid SA.121308, published 1 Apr 2026; Commission decision adopted 6 Mar 2026. Romanian Modernisation Fund scheme for standalone battery-storage installations; overall budget RON 764.295 million, direct-grant form, duration through 31 Dec 2030.
  10. S10
    ANRE — Removal of duplicate regulated charges for stored and reinjected electricity, 8 Jul 2025. Used for specified exemptions on stored/reinjected electricity and the continuing tariff treatment of storage own consumption and technological losses.
  11. S11
    Romanian Ministry of Energy — Order No. 1120/26 July 2024 approving the CfD state-aid scheme. Primary scheme reference used to anchor the Romanian CfD framework; executed project contracts and later auction documentation remain controlling for project-specific settlement.